Contract No: HK/2011/07 Wanchai
Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 2) Environmental Permit no.
EP-122/2002/D Monthly
Environmental Monitoring & Audit Report
- JuLY 2013 -
|
CLIENTS: |
|
Civil Engineering and Development Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
8 August 2013 |
2.2 Scope
of the Project and Site Description
2.3 Project
Organization and Contact Personnel
3 status of regulatory compliance
3.1 Status
of Environmental Licensing and Permitting under the Project
6.3 Review of the
Reasons for and the Implications of Non-compliance
6.4 Summary of action
taken in the event of and follow-up on non-compliance
7 Cumulative Construction Impact due to the
Concurrent Projects
9 Complaints,
Notification of Summons and Prosecution
lIST OF TABLES
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Contact
Details of Key Personnel
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Table 4.1 Continuous
Noise Monitoring Stations
Table 4.2 Air
Monitoring Stations
Table 5.1 Continuous
Noise Monitoring Stations for Contract no. HK/2012/08
Table 5.2 Air
Monitoring Station for Contract no. HK/2012/08
Table 5.3 Details
of Waste Disposal for Contract no. HK/2012/08
Table 8.1
Summary of Environmental Inspections for Contract no. HK/2012/08
Table 9.1 Cumulative
Statistics on Complaints
Table 9.2 Cumulative
Statistics on Successful Prosecutions
LIST OF FIGURES
Figure
2.1 Project
Layout
Figure
2.2 Project
Organization Chart
Figure 4.1 Locations
of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental
Mitigation Implementation Schedule
Appendix 4.1 Action
and Limit Level
Appendix
4.2 Copies
of Calibration Certificates
Appendix
5.1 Monitoring
Schedule for Reporting Month and Coming month
Appendix 5.2 Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.3 Continuous
Noise Monitoring
Results and Graphical Presentations
Appendix 6.1 Event
Action Plans
Appendix 6.2 Notification of
Exceedance
Appendix
9.1 Complaint
Log
Appendix
10.1 Construction
Programme of Individual Contracts
Contract no. HK/2012/08 – Wan
Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Site preparation works
·
Site survey
·
Temporary works
·
Utilities / cooling mains diversion
·
Construction of interim landing step
Noise Monitoring
Air Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
Site Inspections and Audit
Future Key Issues
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West
·
Excavation
for Utilities/ cooling mains diversion
·
Construction
of interim landing steps
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed take up the role as the
Environmental Team (ET) under Environmental Permit no. EP-122/2002/D to implement the Environmental
Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual
of the approved Environmental Impact Assessment (EIA) Report for Central
Reclamation Phase III - Studies, Site Investigation, Design and Construction
(Register No.: AEIAR-040/2001) since 1
May 2013.
1.1.2.
This report documents the finding of EM&A works for Environmental Permit (EP) no. EP-122/2002/D, during
the period of July 2013. The cut-off date of reporting is the last day
of each reporting month
Section
1 Introduction –
details the scope and structure of the report.
Section
2 Project
Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance –
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements – summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results – summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit – summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects – summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection –
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
– summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
10 Conclusion
2.1.1
Central Reclamation Phase III - Studies, Site
Investigation, Design and Construction (hereafter called “the Project”) are
Designated Project (DP) under the Environmental Impact Assessment Ordinance
(Cap. 499) (EIAO). The Environmental Impact Assessment (EIA) Reports for Central
Reclamation Phase III - Studies, Site Investigation, Design and Construction
(Register No. AEIAR-040/2001) has been approved on 31 August 2001.
2.2.1.
The design and construction of Central Reclamation
Phase III involves the permanent reclamation and construction and operation of
a trunk road and its road tunnel that is shown at Figure 2.1.
2.2.2.
The key purpose of the study
area encompasses the area of
·
Reclamation and
seawalls, roads and associated services, North Island Line Protection Works and
Advance Trunk Road Tunnel (ATRT) for the CWB;
·
Reprovisioning
of Star Ferry Pier, public landing steps, wallah wallah moorings, and motor
boat/launch operators' kiosks;
·
External cooling
water systems which consist of the cooling water pumping shells for future
developments, and the reprovisioning of existing cooling water pumping stations
and associated pipework systems and E&M works;
·
Reprovisioning
of existing Leisure and Cultural Services Department (LCSD)'s facilities;
·
Provision of a
flood relief path, stormwater culvert extensions, upgrading of hinterland
stormwater drainage resulting from the reclamation, demolition of the existing
waterfront structures and necessary landscaping;
·
The Hong Kong
Station Extended Overrun Tunnel (EOT) and associated ventilation structures
entrusted for construction within the CRIII works;
·
Reprovisioning
of the Government Heliport at the Wan Chai PCWA and reprovisioning of the Wan
Chai PCWA at
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs)
to be granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the four individual DPs under this Project. Figure 2.1
shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
DP1 |
Central-Wanchai Bypass (CWB) |
Schedule 2, Part I, A.7 |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
DP3 |
Reclamation works |
Schedule 2, Part I, C.1 |
DP4 |
The |
Schedule 2, Part I, A.7 |
2.2.4.
The designated project work I (DP1) was awarded to
China State-Leader Joint Venture HK/2012/08 as part of the Project works by the
Civil Engineering and Development Department (CEDD). The
construction work under Contract no. HK/2012/08 was commenced on 27 May 2013.
2.3.1
Civil Engineering
and Development Department is the overall
project controllers for the Central Reclamation Phase
III Project. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.3.2
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.2:
Table 2.2 Contact
Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3922 3388 |
3912 3010 |
|
|
Contractor under Contract no. HK/2012/08 |
Project Director |
Mr. Andrew TSE |
9137 1811 |
2877 1522 |
Project Manager |
Mr. Victor WU |
9193 8871 |
|||
Deputy Project Manager |
Mr. George CHEUNG |
9268 1918 |
|||
Site Agent |
Mr. Paul LUI |
9095 7922 |
|||
Environmental Officer |
Mr. James MA |
9130 9549 |
|||
Environmental
Supervisor |
Mr. Ching Man, CHAN |
6050 4919 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.3.3
In this reporting month, the
principal work activities of the contract is included as follows:
Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan
Chai Bypass at Wan Chai West
·
Site
preparation works
·
Site
survey
·
Temporary
works
·
Utilities
/ cooling mains diversion
·
Construction
of interim landing step
2.3.4
In coming reporting month, the
principal work activities of the contract is anticipated as follows:
Contract no. HK/2012/08 – Wan
Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West
·
Excavation
for Utilities/ cooling mains diversion
·
Construction
of interim landing steps
3.1.1.
A
summary of the current status on licences and/or permits on environmental protection
pertinent to the Project is shown in Table 3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-122/2002/D |
1 Sep
2009 |
Valid |
3.1.2.
The
current status on licences and/or permits on environmental protection pertinent
for contract no. HK/2012/08 showed in Table 3.2.
Table 3.2 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-134-C3790-01 |
8 Mar 2013 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Construction Noise Permit |
GW-RS0659-13 |
24 Jun 2013 |
1 Jul 2013 to 22 Dec 2013 |
Valid |
|
GW-RS0730-13 |
5 Jul 2013 |
6 Jul 2013 to 4 Jan 2014 |
Valid |
NOISE Monitoring Stations
4.1.1.
The
continuous noise monitoring station for the Project is listed and shown in Table
4.1 and Figure 4.1.. Appendix
4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.1 Continuous Noise Monitoring Stations
District |
Station |
Description |
Central |
ACL3 |
City
Hall |
Noise Monitoring Parameters, Frequency and Duration
4.1.2.
Continuous 24-hour noise monitoring shall be
carried out at the designated monitoring stations. The following is an initial
guide on the regular monitoring frequency for each station on a 24 hours daily
basis when noise generating activities are underway:
·
One set of
measurements between 0700 and 1900 hours on normal weekdays.
·
One set of
measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300
hours on public holidays.
·
One set of
measurements between 2300 and 0700 hours on next day on everyday.
4.1.3.
If construction works are extended to include works
during the hours of 1900 – 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.4.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agrees to within 1.0 dB.
4.1.5.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
4.1.6.
The sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency before deployment to the site and during each site visit.
Measurements will be accepted as valid only if the calibration level from
before and after the noise measurement agrees to within 1.0 dB.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.2 and Figure 4.1.. Appendix
4.1 shows the established Action/Limit Levels for the
monitoring works.
Table 4.2 Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
ACL1 |
City
Hall |
Central |
ACL2 |
PLA Barracks |
Central |
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6 – 1.7 m3
per minute adjustable flow range;
·
Equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
·
Installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable of
providing a minimum exposed area of 406 cm2;
·
Flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped with a
shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped with a
flow recorder for continuous monitoring;
·
Provided with a
peaked roof inlet;
·
Incorporated
with a manometer;
·
Able to hold and
seal the filter paper to the sampler housing at horizontal position;
·
Easily changeable
filter; and
·
Capable of
operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
4.2.9.
After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity controlled
chamber followed by accurate weighing by an electronic balance with readout
down to 0.1 mg. The balance shall be regularly calibrated against a traceable
standard.
4.2.10. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
4.2.11. Current
calibration certificates of equipments are presented in Appendix 4.2.
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designated project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure
4.1. The monitoring results are presented in according to
the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contract is:
Contract no. HK/2012/08 – Wan Chai Development
Phase II – Central – Wan Chai Bypass at Wan Chai West.
5.0.3.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix 5.1.
5.1.1
Due
to safety concerned, the location of the continuous noise monitoring station at
City Hall was finely adjusted to the roof of the City Hall, Low Block on 1 May
2013.
5.1.2
The
proposed division of noise monitoring stations is summarized in Table 5.1
below.
Table 5.1 Continuous
Noise Monitoring Stations for Contract
no. HK/2012/08
Location ID |
District |
Description |
ACL3 |
Central |
City Hall |
Remarks: Continuous
noise monitoring results and graphical presentation for ACL3 during restricted
hours and night time period are for information only.
5.1.3
No
exceedance was recorded at ACL3 - City Hall in this reporting month.
5.1.4
Continuous
noise monitoring results measured in this reporting period are reviewed and
summarized. Details of continuous noise monitoring results and graphical
presentation can be referred to Appendix 5.3 .
5.2.1
The proposed division of air monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Air Monitoring Station for Contract
no. HK/2012/08
Station |
Description |
ACL1 |
City Hall |
ACL2 |
PLA Barracks |
5.2.2
No action or limit level exceedance was recorded at
ACL1 – City Hall and ACL2 PLA Barracks in the reporting month.
5.2.3
The Air quality monitoring results measured in this
reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.2.
5.3.1
Inert and Non-inert C&D wastes were disposed in
this reporting month. Details
of the waste flow table are summarized in Table 5.3.
Table 5.3 Details
of Waste Disposal for Contract no. HK/2012/08
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
6 |
288 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Non-inert C&D materials disposed, m3 |
20 |
25 |
SENT Landfill |
Non-inert C&D materials recycled, m3 |
NIL |
NIL |
NIL |
Chemical waste disposed, kg |
NIL |
NIL |
NIL |
6.0.1.
The Event Action Plan for construction noise and
air quality are presented in Appendix
6.1.
6.1.1.
No exceedance was recorded at ACL3 – City Hall in
this reporting month.
6.2.1.
No action or limit level exceedance was recorded at
ACL1 – City Hall and ACL2 – PLA Barracks in this reporting month.
6.3.1.
There was no non-compliance from the site audits in
the reporting period. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.4.1
There was no particular action taken since no
non-compliance was recorded from the site audits in the reporting period.
7.0.1.
This section addresses the relevant cumulative
construction impact due to the concurrent activities of the current projects
including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase
II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects
(IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan
Chai East (CWB Tunnel).
7.0.2.
According to the Monthly EM&A report (June 2013)
of Central Reclamation Phase III (CRIII) for Contract HK 12/02, underground
drainage and footpath construction, modification to the junction of Road D8 and
Road P2 and modification of timber decks at advance promenade were performed in
the July 2013 reporting month. The water quality monitoring was completed in
October 2011 and no Project-related exceedance was recorded for air and noise
monitoring. It can be concluded
that cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 was insignificant.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activity under Wan Chai Development Phase II were
marine works at HKCEC areas, cross-harbour Watermains, Fresh Watermains and
Cooling Watermains Installations, tunnel works at Wan Chai East, ELS work and
pipe roofing works at TS4 and cut and cover tunnel construction at TPCWAE. Excavation
and tunnel works at Central Interchange, ELS and box culvert construction at
North Point area. The major environmental impact was water quality impact at
7.0.4.
The major environmental impacts generated from tunnel
works at Central and tunnel works at Wan Chai East, IECL and Causeway Bay Typhoon
Shelter were undertaken in the reporting month. No significant air impact from
construction activities was anticipated in the reporting month. Besides, no project-related
exceedances were recorded during the air and noise environmental monitoring
events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II was insignificant.
8.0.1.
Five site inspections for Contract no. HK/2012/08 was carried out on 2, 9,
16, 23 and 30 July
Table 8.1 Summary of
Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
130709_01 |
9-Jul-13 |
Chemical container should be properly stored
or cleared as chemical waste |
Chemical containers have been removed |
Completion as observed on 16 July 2013 |
9.0.1.
No environmental complaint was received in the
reporting period.
9.0.2.
The
details of cumulative complaint log and updated summary of complaints are
presented in Appendix 9.1
9.0.3.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table 9.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
May 2013 |
0 |
June 2013 |
0 |
July 2013 |
0 |
Total |
0 |
Table 9.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1. The construction
programmes of individual contracts are provided in Appendix 10.1.
Table 10.1 Summary of Key Construction
Activities of Individual Contract(s) to be commenced in Coming Reporting Month
Contract
No. |
Key Construction Works |
Recommended
Mitigation Measures |
HK/2012/08 |
·
Excavation
for Utilities/ cooling mains diversion ·
Construction
of interim landing steps |
·
Dust
control during dust generating works ·
Provision
of protection to ensure no runoff out of site area or direct discharge into
public drainage system. |